Water Main Project
The Town of Richey is currently working on a water main replacement project to address leakage, breaks and replace aging water mains. The projects shown here are critical to achieving that goal. The information provided on this page will provide all relevant information regarding the improvements to the Town's water infrastructure.
Key Improvements Areas To Be Addressed:
- High Water Loss
- Above Average Leak Repairs
- Inadequate Hydrants and Valves
- Low Fire Flows
- Inadequate Curb Stops
- Low Storage
Phase 01: Projected Progress
- Phase 01 Construction ETA: April 2023
- Phase 01 Project Status: Awaiting Construction
- Engineering Company: GreatWest Engineering
- Construction Company: COP Construction
Phase 02: Projected Progress
- Phase 02 Construction ETA: Summer 2024-2025
- Phase 02 Project Status: Awaiting Funding
- Engineering Company: GreatWest Engineering
- Construction Company: TBD
Phase 2 Funding Plan (Phased Approach)
TSEP Grant | $ 500,000 |
DNRC Grant | $ 125,000 |
CDBG Grant | $ 600,000 |
SRF Loan | $ 312,500 |
SRF Forgiveness | $ 312,500 |
Total: | $ 1,850,000 |
* Project will be up to 83% Grant Funded
Funding Plan (Target Rates)
Current Water / Sewer Rate | $ 99.86 / Month |
Current MHI | $ 60,000 |
Combined Target Rate | $ 115.00 / Month |
Operating costs Require | $ 125.00 / Month |
* Rate Increase of $26.00 per month needed to meet operating cost.
To Obtain Grants, the Town of Richey Must meet or exceed the Target Rate.
CDBG Eligibility (Per 2022 Income Survey)
- Richey Median Household Income = $60,000
- Richey Low-to-Moderate Income = 64%
Phase 02: Potential Schedule
Schedule is dependent on funding strategy:
- MCEP Funds available in July, 2023.
- DNRC / RRGL Funds available in July, 2023.
- SRF Funds available in 2023.
- Engineering Design = 3 Months
- DEQ/RD Review = 3 Months
- Bidding = 1 Month
- Construction = Up to 4 Months. Done in Summer, 2024-2025.